FEATURED PROJECT

Mina Sur Leach Pad Stacking and Reclaiming System

Client: Bechtel-ARA
Owner: CODELCO
Design Capacity: 2300 mtph

We commissioned this system in Chile. The system is an integral part of CODELCO’s Plant Tratamiento Minerales Pilas Project (PTMP), an expansion of the facilities at Chuquicamata.

We supplied the original stacking system at Chuquicamata- Mina Norte. The equipment provided includes a 1955 m Stacking Feed Conveyor, a 377 m Mobile Conveyor, 382 m Mobile Reclaiming Conveyor and a 2217 m Overland Conveyor. All conveyors have trippers or hoppers depending on their functionality.

For this project, FLS RAHCO supplied all logistical support including turnkey installation.■

Mina Sur 1
Mina Sur 2
Mina Sur 3